UPS shift away from Amazon shows bigger payoff Lanesurf: 62% of Loads Get Vetted Carrier Offers Before Brokers Arrive India-China Border Trade Via Lipulekh Resumes Aug 1; China Permits 20 Traders Geopolitics Drives CMA CGM Q2 Profit Surge of 42% as Volumes and Rates Climb Benchmark Diesel Price Rises Third Week as Futures Plunge; Spread Hits Record Indian Government Limits Sugar Dealers to 400 Tonnes Stock Until November to Curb Hoarding Tenants signing longer leases for larger warehouses as 3PLs lock in capacity US stock market flat as S&P 500 and Dow barely move, Nasdaq slides over 1% on chip rout TruAlt Bioenergy Q1 Net Zooms to ₹59.27 Crore on Higher Revenues, Capacity Expansion India’s cotton sowing crosses 100 lakh hectares as monsoon picks up, area expands in key states UPS shift away from Amazon shows bigger payoff Lanesurf: 62% of Loads Get Vetted Carrier Offers Before Brokers Arrive India-China Border Trade Via Lipulekh Resumes Aug 1; China Permits 20 Traders Geopolitics Drives CMA CGM Q2 Profit Surge of 42% as Volumes and Rates Climb Benchmark Diesel Price Rises Third Week as Futures Plunge; Spread Hits Record Indian Government Limits Sugar Dealers to 400 Tonnes Stock Until November to Curb Hoarding Tenants signing longer leases for larger warehouses as 3PLs lock in capacity US stock market flat as S&P 500 and Dow barely move, Nasdaq slides over 1% on chip rout TruAlt Bioenergy Q1 Net Zooms to ₹59.27 Crore on Higher Revenues, Capacity Expansion India’s cotton sowing crosses 100 lakh hectares as monsoon picks up, area expands in key states
Home ›› Commodities ›› Commodities Energy ›› Crown Estate Launches Accelerated Tender for 1.5GW Morgan Offshore Wind Site in Irish Sea

Crown Estate Launches Accelerated Tender for 1.5GW Morgan Offshore Wind Site in Irish Sea

The Crown Estate has launched an accelerated tender for the 1.5GW Morgan offshore wind site in the Irish Sea, following the withdrawal of EnBW and JERA Nex BP. Bidders will compete via a rising-clock auction for a site exclusivity fee, with potential developer selection by end of 2026. The project already has a development consent order from August 2025.

iG
iGEN Editorial
July 27, 2026
Crown Estate Launches Accelerated Tender for 1.5GW Morgan Offshore Wind Site in Irish Sea

The Crown Estate has launched an accelerated tender for the 1.5GW Morgan offshore wind site in the Irish Sea, with a replacement developer potentially selected by the end of the year, according to Splash247.

Background and Developer Withdrawal

The tender follows the withdrawal of EnBW and JERA Nex BP from the project earlier in 2026. In June 2026, the Crown Estate confirmed its intention to return the site to the market via a new competitive process. The move aims to quickly fill the gap left by the departing developers.

Development Milestones

Morgan has already passed several key development stages. The wind farm secured a development consent order in August 2025, while a decision on the transmission infrastructure is expected in September 2026. The transmission application was submitted jointly with the grid connection assets for the neighbouring 480MW Morecambe offshore wind project, Splash247 reported.

"By launching an accelerated tender process, we’re offering developers the potential opportunity to take forward a project with substantial consenting and grid progress already in place," said Gus Jaspert, managing director for marine at The Crown Estate.

Tender Process Details

Bidders will compete through a rising-clock auction, with offers determining a site exclusivity fee. The successful developer will only begin paying the fee once the project enters into lease, with the lump-sum amount spread over 20 years from the lease commencement date. The winning bidder will receive seabed rights under a 10-year agreement for lease. Subject to meeting required conditions, the developer will then have the option to enter into a lease covering construction and operation of the offshore wind farm.

The Crown Estate said it could not provide a maximum contract value because the eventual value of the concession to the developer could not be predicted.

Parameter Detail
Site capacity 1.5 GW
Location Irish Sea
Previous developers EnBW, JERA Nex BP
Development consent August 2025
Transmission decision expected September 2026
Auction method Rising-clock
Payment start On lease entry
Payment period 20 years from lease commencement
Initial lease term 10-year agreement for lease
Developer selection target End of 2026

Separate from Round 6

The Morgan tender is separate from the sixth offshore wind leasing round, which will offer around 6GW of capacity off northeast England and is expected to begin in the first half of 2027, Splash247 reported.

For commodity traders and energy analysts, this tender represents an opportunity to monitor offshore wind investment trends in the UK, which affect long-term power generation mix and renewable energy certificate markets. The accelerated process reduces development risk for the winning bidder, potentially influencing project finance structures and equipment procurement timelines.


Sources: Splash247 Maritime