Home ›› Logistics ›› Shipping Freight ›› Shipping Lines ›› HMM to spend $135M expanding Washington United Terminals at Port of Tacoma

HMM to spend $135M expanding Washington United Terminals at Port of Tacoma

HMM has contracted HD Hyundai Samho to supply four cranes for Washington United Terminals at the Port of Tacoma, replacing two aging quay cranes and adding two new yard cranes. The $135 million expansion will raise annual capacity from 590,000 to 880,000 TEUs, with cranes due in 2028 and full completion expected in 2030.

iG
iGEN Editorial
August 7, 2026
HMM to spend $135M expanding Washington United Terminals at Port of Tacoma

HMM (011200.KS), the Seoul-based ocean carrier formerly known as Hyundai Merchant Marine and the world's eighth-largest liner operator, has signed a contract with HD Hyundai Samho of South Korea for four new cranes at Washington United Terminals (WUT) at the Port of Tacoma, according to FreightWaves. HMM and HD Hyundai Samho are separate companies in different corporate groups. Under the contract, WUT will replace two aging quay cranes and add two new yard cranes. The upgrade will enable the terminal to handle large containerships and increase annual capacity from 590,000 twenty-foot equivalent units (TEUs) to 880,000 TEUs, significantly strengthening its competitiveness, FreightWaves reported.

Contract with HD Hyundai Samho

Opened in 1999, WUT is operated by HMM, according to FreightWaves. The crane contract with HD Hyundai Samho covers four machines, and delivery is scheduled for 2028. HMM and HD Hyundai Samho are separate companies and belong to different corporate groups, the report noted.

Cranes, capacity and timing

The Northwest Seaport Alliance, in a release reported by local media, put the overall WUT investment at $135 million, with full project completion anticipated in 2030, according to FreightWaves. WUT does not publicly disclose annual terminal throughput.

Metric Detail
Cranes under contract 4
Replacement quay cranes 2
New yard cranes 2
Capacity before upgrade 590,000 TEUs
Capacity after upgrade 880,000 TEUs
Crane delivery 2028
Full project completion 2030
Total investment $135 million

On-dock rail and West Coast routes

HMM highlighted the terminal's on-dock rail system as the strategic reason for the investment. In an announcement carried by FreightWaves, the carrier said:

Equipped with an on-dock rail system for handling rail cars, the terminal offers excellent inland logistics connectivity, creating strong synergies with our U.S. West Coast routes.

The on-dock rail setup handles rail cars at the terminal, which HMM said gives WUT excellent inland logistics connectivity and strong synergies with its U.S. West Coast routes.

Shipper and operator implications

The expansion adds 290,000 TEUs of annual capacity at WUT, roughly 49% above the current 590,000-TEU level. HMM said the new cranes will enable the terminal to handle large containerships, a key capability for ocean carriers deploying bigger vessels. Because WUT does not publicly disclose throughput, the 2028 crane delivery and the 2030 completion date are the concrete milestones for when the added capacity comes online.

Watch list

Upcoming factors reported by FreightWaves:

  • Delivery of the four cranes from HD Hyundai Samho is scheduled for 2028.
  • Full project completion is anticipated in 2030, per the Northwest Seaport Alliance.
  • Annual terminal capacity is set to rise from 590,000 to 880,000 TEUs.
  • Throughput is not publicly disclosed, so post-expansion utilization will not be visible in WUT's own reporting.

Sources: FreightWaves

Keep Reading

Recommended Stories

MSC Acquires Majority Stake in Pivdennyi Terminal Logistics

MSC Acquires Majority Stake in Pivdennyi Terminal

Mediterranean Shipping Co (MSC) has reportedly acquired a 51% stake in the Transinvestservice Container Terminal in Pivdennyi, Ukraine. This acquisition marks MSC's second terminal asset in the country, potentially revitalizing operations at the port.

June 4, 2026
East Asia faces $890bn maritime investment bill to 2040, World Bank warns Logistics

East Asia faces $890bn maritime investment bill to 2040, World Bank warns

The World Bank estimates East Asia and the Pacific needs about $890bn through 2040 to modernize ports, replace aging fleets and build alternative-fuel supply chains. Ports need $12bn annually, container capacity may nearly double, and China accounts for 65% of port spending. The report warns that regulatory uncertainty has led to sectoral paralysis.

July 31, 2026
PSA to invest in new deepsea container hub in northern Vietnam Logistics

PSA to invest in new deepsea container hub in northern Vietnam

PSA Vietnam has signed an agreement to invest in four deepsea container berths at Lach Huyen Port in Haiphong, with a total capacity of 4.5 million TEU. The first two berths are expected to start development at the end of 2026 and be completed in 2028, with full completion by 2035. The investment supports PSA's node-to-network strategy and complements existing inland container depot facilities in Bac Ninh.

July 3, 2026
New Commissioner Completes U.S. Maritime Regulator Panel Logistics

New Commissioner Completes U.S. Maritime Regulator Panel

Robert J. Harvey's swearing-in as a commissioner restores the Federal Maritime Commission to full capacity, potentially impacting U.S. maritime regulations. This change could influence ocean freight rates and port operations.

June 2, 2026