OpenAI’s Rogue AI Agent Hacked More Than Just Hugging Face Inside the rogue ChatGPT hack of Hugging Face: AI agents operate at superhuman speed but make clumsy mistakes Landstar Expects to Emerge a Winner After Supreme Court’s Montgomery Ruling Widens Broker Liability New Senate bill targets 'chameleon carriers' that reopen to escape penalties Werner Enterprises Posts Highest Revenue Per Truck Growth in One-Way Segment in a Decade CMA CGM and Stonepeak Launch United Ports LLC in $2.4 Billion Terminal Joint Venture UPS shift away from Amazon shows bigger payoff Lanesurf: 62% of Loads Get Vetted Carrier Offers Before Brokers Arrive India-China Border Trade Via Lipulekh Resumes Aug 1; China Permits 20 Traders Geopolitics Drives CMA CGM Q2 Profit Surge of 42% as Volumes and Rates Climb OpenAI’s Rogue AI Agent Hacked More Than Just Hugging Face Inside the rogue ChatGPT hack of Hugging Face: AI agents operate at superhuman speed but make clumsy mistakes Landstar Expects to Emerge a Winner After Supreme Court’s Montgomery Ruling Widens Broker Liability New Senate bill targets 'chameleon carriers' that reopen to escape penalties Werner Enterprises Posts Highest Revenue Per Truck Growth in One-Way Segment in a Decade CMA CGM and Stonepeak Launch United Ports LLC in $2.4 Billion Terminal Joint Venture UPS shift away from Amazon shows bigger payoff Lanesurf: 62% of Loads Get Vetted Carrier Offers Before Brokers Arrive India-China Border Trade Via Lipulekh Resumes Aug 1; China Permits 20 Traders Geopolitics Drives CMA CGM Q2 Profit Surge of 42% as Volumes and Rates Climb
Home ›› Regulations Compliance ›› Product Standards ›› MNRE Allows Provisional Commissioning for Solar Projects Awaiting ALMM List-II Approval

MNRE Allows Provisional Commissioning for Solar Projects Awaiting ALMM List-II Approval

The Ministry of New and Renewable Energy (MNRE) has provided temporary relief to solar projects awaiting ALMM List-II approval, allowing provisional commissioning for one month from June 23, 2026. Projects installed before June 1, 2026, with pending exemption applications may generate and inject electricity while their requests are processed. Authorities are directed not to withhold commissioning approvals solely due to pending ALMM clearance.

iG
iGEN Editorial
June 23, 2026
MNRE Allows Provisional Commissioning for Solar Projects Awaiting ALMM List-II Approval

Effective June 23, 2026, the Ministry of New and Renewable Energy (MNRE) issued an office memorandum allowing provisional commissioning of solar projects that are awaiting approval under the Approved List of Models and Manufacturers (ALMM) List-II, providing temporary relief to developers facing regulatory uncertainty.

What Changed

In an office memorandum dated June 23, 2026, MNRE ruled that projects installed before June 1, 2026 but unable to commission due to delays in obtaining ALMM-related approvals may be granted provisional commissioning while their exemption requests are under consideration. This clarification follows an earlier decision in which MNRE stated that no blanket extension would be granted beyond June 1 for compliance with ALMM List-II requirements. According to the source, several implementing agencies, distribution companies, and state authorities had subsequently withheld commissioning approvals for projects whose exemption applications were still pending.

The one-month window allows projects that have already applied for ALMM List-II exemption through the MNRE portal and are awaiting a decision to be provisionally commissioned.

Who Is Affected

This relief directly impacts:

  • Solar project developers that installed systems before June 1, 2026 but could not commission them due to pending ALMM approvals.
  • Implementing agencies, distribution companies, and state authorities that were withholding commissioning approvals, recognition of commercial operation date (COD), State Load Dispatch Centre (SLDC) registrations, or open-access permissions.
  • Renewable energy investors concerned about stranded capacity.

The relief is not a blanket extension; it only applies to projects that have already submitted an exemption application through the MNRE portal and are awaiting a decision.

Compliance Obligations and Deadlines

To benefit from the provisional commissioning relief, project developers must:

  1. Have installed the solar project before June 1, 2026.
  2. Have submitted an ALMM List-II exemption application via the MNRE portal prior to the memorandum.
  3. Ensure their applications remain pending a final decision from MNRE.

The provisional commissioning is valid for one month from June 23, 2026. During this period, eligible projects are permitted to generate, inject, wheel, bank, and settle electricity under applicable regulations.

Authorities are directed not to withhold commissioning approvals, COD recognition, SLDC registrations, or open-access permissions solely because an ALMM exemption application remains pending.

Provision Details
Effective date of memorandum June 23, 2026
Installation deadline for eligibility Before June 1, 2026
Required action Exemption application submitted via MNRE portal, awaiting decision
Relief duration One month from June 23, 2026
Permitted activities Generation, injection, wheeling, banking, settlement
Authorities’ obligation Not to withhold approvals due to pending ALMM exemption

Industry Implications

According to the source, the move is expected to prevent already-installed solar capacity from remaining stranded while the government processes pending ALMM exemption requests. For project developers, the one-month window provides a buffer to start generating revenue and avoid financial losses associated with idle assets. Implementing agencies and distribution companies must adjust internal processes to comply with the directive and avoid unnecessary delays. The MNRE office memorandum serves as the primary guidance document for all stakeholders navigating this interim period.


Sources: Policy-TOI

Keep Reading

Recommended Stories

Pacifico Energy Korea Signs Local Supply Deal for 3.2 GW Jindo Offshore Wind Cluster Commodities

Pacifico Energy Korea Signs Local Supply Deal for 3.2 GW Jindo Offshore Wind Cluster

US-based offshore wind developer Pacifico Energy Korea has signed a memorandum of understanding with three offshore wind suppliers in the Gwangyang Bay area to support the 3.2 GW Jindo offshore wind project cluster. The deal aims to strengthen domestic sourcing, support regional industry, and build Gwangyang Bay into a wider offshore wind supply hub.

July 10, 2026
Adani Group AGM: Gautam Adani Unveils 10 GW Nuclear Plan, Record Infrastructure Spend Business

Adani Group AGM: Gautam Adani Unveils 10 GW Nuclear Plan, Record Infrastructure Spend

At the Adani Group AGM, chairman Gautam Adani announced plans to develop 10 GW of nuclear power capacity by 2035 via Adani Atomic Energy. He highlighted a record Rs 1.5 lakh crore infrastructure spend in FY26 and expansion across power, transmission, and low-carbon energy. The group aims to increase power generation capacity to 45 GW in five years.

July 8, 2026
Norwegian Føn Energy Services Wins Multi-Year O&M Deal for Poland's Baltic Power Offshore Wind Farm Commodities

Norwegian Føn Energy Services Wins Multi-Year O&M Deal for Poland's Baltic Power Offshore Wind Farm

Aker-backed Føn Energy Services has secured a multi-year balance-of-plant O&M contract for the 1.2GW Baltic Power offshore wind farm in Poland, the country's first such project. The deal covers subsea asset maintenance and environmental surveys. Local content is expected to exceed 21%, with Polish suppliers already active across the supply chain.

July 8, 2026
El Nino Weakens India Hydropower to Steepest Drop Since Feb 2024, Strains Grid Commodities

El Nino Weakens India Hydropower to Steepest Drop Since Feb 2024, Strains Grid

India's hydropower generation fell more than 20% in June, the steepest year-on-year drop since February 2024, as El Nino conditions caused a 38% rainfall deficit. Reservoir levels are critically low, forcing greater reliance on coal-fired power. The weak monsoon also hurt kharif crop sowing, with oilseeds acreage down 39% and cotton down 23%.

July 7, 2026