MNRE Allows Provisional Commissioning for Solar Projects Awaiting ALMM List-II Approval

The Ministry of New and Renewable Energy (MNRE) has provided temporary relief to solar projects awaiting ALMM List-II approval, allowing provisional commissioning for one month from June 23, 2026. Projects installed before June 1, 2026, with pending exemption applications may generate and inject electricity while their requests are processed. Authorities are directed not to withhold commissioning approvals solely due to pending ALMM clearance.

iG
iGEN Editorial
June 23, 2026
MNRE Allows Provisional Commissioning for Solar Projects Awaiting ALMM List-II Approval

Effective June 23, 2026, the Ministry of New and Renewable Energy (MNRE) issued an office memorandum allowing provisional commissioning of solar projects that are awaiting approval under the Approved List of Models and Manufacturers (ALMM) List-II, providing temporary relief to developers facing regulatory uncertainty.

What Changed

In an office memorandum dated June 23, 2026, MNRE ruled that projects installed before June 1, 2026 but unable to commission due to delays in obtaining ALMM-related approvals may be granted provisional commissioning while their exemption requests are under consideration. This clarification follows an earlier decision in which MNRE stated that no blanket extension would be granted beyond June 1 for compliance with ALMM List-II requirements. According to the source, several implementing agencies, distribution companies, and state authorities had subsequently withheld commissioning approvals for projects whose exemption applications were still pending.

The one-month window allows projects that have already applied for ALMM List-II exemption through the MNRE portal and are awaiting a decision to be provisionally commissioned.

Who Is Affected

This relief directly impacts:

  • Solar project developers that installed systems before June 1, 2026 but could not commission them due to pending ALMM approvals.
  • Implementing agencies, distribution companies, and state authorities that were withholding commissioning approvals, recognition of commercial operation date (COD), State Load Dispatch Centre (SLDC) registrations, or open-access permissions.
  • Renewable energy investors concerned about stranded capacity.

The relief is not a blanket extension; it only applies to projects that have already submitted an exemption application through the MNRE portal and are awaiting a decision.

Compliance Obligations and Deadlines

To benefit from the provisional commissioning relief, project developers must:

  1. Have installed the solar project before June 1, 2026.
  2. Have submitted an ALMM List-II exemption application via the MNRE portal prior to the memorandum.
  3. Ensure their applications remain pending a final decision from MNRE.

The provisional commissioning is valid for one month from June 23, 2026. During this period, eligible projects are permitted to generate, inject, wheel, bank, and settle electricity under applicable regulations.

Authorities are directed not to withhold commissioning approvals, COD recognition, SLDC registrations, or open-access permissions solely because an ALMM exemption application remains pending.

Provision Details
Effective date of memorandum June 23, 2026
Installation deadline for eligibility Before June 1, 2026
Required action Exemption application submitted via MNRE portal, awaiting decision
Relief duration One month from June 23, 2026
Permitted activities Generation, injection, wheeling, banking, settlement
Authorities’ obligation Not to withhold approvals due to pending ALMM exemption

Industry Implications

According to the source, the move is expected to prevent already-installed solar capacity from remaining stranded while the government processes pending ALMM exemption requests. For project developers, the one-month window provides a buffer to start generating revenue and avoid financial losses associated with idle assets. Implementing agencies and distribution companies must adjust internal processes to comply with the directive and avoid unnecessary delays. The MNRE office memorandum serves as the primary guidance document for all stakeholders navigating this interim period.


Sources: Policy-TOI

Keep Reading

Recommended Stories

I Tested Portable Solar Panels for Years to See Which Models Best Deliver Free Electricity Technology

I Tested Portable Solar Panels for Years to See Which Models Best Deliver Free Electricity

WIRED's Simon Hill tested portable solar panels over several years and found the Jackery Solar Saga 200 the most effective, delivering up to 170 watts and charging a 4,085Wh power station in two days. Bluetti's 350-W and 500-W panels provide higher output but with more finicky setup. The review details efficiencies, IP ratings, and connector standards.

August 10, 2026
Clean power push: India hits 300 GW non-fossil capacity milestone ahead of 2030 target Commodities

Clean power push: India hits 300 GW non-fossil capacity milestone ahead of 2030 target

India crossed 300.50 GW of non-fossil fuel-based electricity capacity as of July 31, accounting for more than 54% of total installed power capacity and over 60% of the 500 GW target for 2030. Solar leads the mix at 164.59 GW, with record additions of 55.29 GW in 2025-26. Domestic solar module manufacturing capacity also crossed 200 GW.

August 9, 2026
I Tested a Pile of Solar Generators to See Which Are Worth the Money Technology

I Tested a Pile of Solar Generators to See Which Are Worth the Money

August 8, 2026
Energy Secretary signals Jones Act waiver extension as pump prices remain elevated Logistics

Energy Secretary signals Jones Act waiver extension as pump prices remain elevated

U.S. Energy Secretary Chris Wright said another temporary Jones Act waiver extension is likely, as the existing exemption has helped lower fuel prices in California and the East Coast. The current waiver expires August 16, and the White House is expected to extend it, though analysts say the impact on pump prices is small. Maritime groups and some Republican lawmakers oppose further extensions.

August 5, 2026